With mayoral approval or a veto override, D.C. would be allowed to pay Capitol Paving for goods and services already received or still to come.
After mayoral approval or a veto override, D.C. would approve Capitol Paving’s contract and two changes and allow payments totaling up to $5 million. The emergency law would last up to 90 days.
D.C. would approve the contract and two changes and authorize payments capped at $5 million total. This covers Capitol Paving contract CW130810 and changes M01 and M02, including goods and services already received or still to come. The approval would bypass section 202 of D.C.’s Procurement Practices Reform Act of 2010, a law governing city contracts. The law would take effect after the Mayor approves it or the Council overrides a veto and would last no longer than 90 days.