Owners with approved tax exemption applications report completed work and planned jobs, and cities check those reports before deciding whether the property qualifies.
After construction, owners with an approved tax exemption must report completed work and planned jobs. Certain federally certified clean energy facilities must also provide labor information and a copy of the workforce or labor agreement used for construction.
Cities check whether completed work and planned jobs match the approved application and contract. For certain clean energy facilities, they also consult the state labor department about available wage and apprentice records.
For a qualifying clean energy facility, a city may allow up to two extra 24-month construction extensions when delays are beyond the owner's control and the owner acts in good faith and with due diligence.
Owners must report completed work and planned jobs to the city after construction. This applies when the owner has an approved tax exemption application for an industrial or manufacturing facility and has received a certificate of occupancy. For a clean energy facility that requires certification by a federal regulatory commission, the owner must also provide labor information and a copy of the executed workforce or labor agreement used for construction. The owner must state that the work was completed within three years of the conditional tax exemption certificate.
Cities must review the owner's statements and, for certain clean energy facilities, consult the state labor department about available labor records. This applies to cities reviewing tax exemption requests for industrial or manufacturing facilities. The labor review applies to a clean energy facility that requires certification by a federal regulatory commission. The city checks available information about wage law compliance, prevailing wages, and registered apprentices. The city must decide within 30 days after receiving the owner's statements. If the property qualifies, the city must file the exemption certificate with the county assessor within 30 days after that review period ends.
A city may extend the construction deadline for up to two additional periods of 24 consecutive months each for certain clean energy facilities. The owner must be seeking a tax exemption for a qualifying clean energy facility. The delay must be beyond the owner's control, and the owner must have acted and be reasonably expected to act in good faith and with due diligence. This option applies to a clean energy facility that requires certification by a federal regulatory commission. Each additional extension may last up to 24 consecutive months.