Tennessee’s law generally bars local governments and electric utilities from covering large data centers’ power infrastructure costs, while allowing limited shared costs and reimbursements.
Local governments and electric utilities generally cannot cover power infrastructure costs caused by large data centers. Exceptions allow certain shared system costs and standard reimbursements that do not raise existing customers’ rates.
Large data centers may buy power from independent producers in Tennessee. Direct connections need written utility approval when the center also uses utility service; shared power lines generally require the owner’s agreement.
Independent producers do not count as public utilities solely because they operate power generation or storage equipment and supply covered data centers under authorized agreements. Other activities may still trigger utility rules.
Local governments and electric utilities generally cannot pay or absorb covered power infrastructure costs for large data centers. Centers must expect peak demand of at least 50 megawatts in their first three years. State-owned or operated facilities are excluded, as are communications-provider facilities mainly serving networks or broadband. Covered costs concern utility-owned or locally owned infrastructure needed because a center is built or expanded. Utilities may assign some costs to shared system improvements only if all four tests are met: improvements exceed the center’s needs, can serve others without reducing existing service, repair or replace infrastructure originally paid for by someone else, and follow utility cost allocation policies. Maintenance also qualifies. Reimbursements must follow standard policies for comparable customers, cannot favor data centers, and cannot raise existing customers’ rates. Federal obligations still apply. Conflicting Tennessee Valley Authority requirements control. Local governments and utilities are not liable for refusing to honor an obligation that is void under this section. The law took effect May 7, 2026. It applies to conduct occurring and contracts or agreements entered into, amended, or renewed on or after that date.
Covered data centers may buy electricity directly from independent power producers located in Tennessee. Centers must meet the 50-megawatt threshold and facility definitions, including the state and communications-provider exclusions. Purchases may include electricity, reserved power capacity, and related services. A direct connection on the center’s side of its meter needs written utility approval if the center also receives utility service. No such approval is required if it receives no utility service. Access to utility or Tennessee Valley Authority power lines depends on the owner’s choice and terms, unless federal law provides otherwise. Federal law applies, and conflicting Tennessee Valley Authority requirements control. These rules apply to conduct occurring and contracts or agreements entered into, amended, or renewed on or after May 7, 2026.
An independent power producer does not count as a public utility solely because it operates power generation or storage equipment and supplies a covered data center under an authorized agreement. Covered producers sell under written agreements to data center owners or operators or wholesale buyers, which buy power for resale. Producers offering these services to other kinds of customers do not meet this definition. The exclusion concerns operating generation or storage equipment in Tennessee and supplying covered centers under authorized agreements. Other activities may still make the producer a public utility. The exclusion applies to conduct occurring and contracts or agreements entered into, amended, or renewed on or after May 7, 2026.