Nevada’s commission must study electric fuel and power costs and report by July 1, 2026, while utilities must repay customers for confirmed overcharges.
The commission must study how electric utilities pass fuel and power costs to customers and ways to reduce rate swings. It may set up a system to share those costs if it finds that is in the public interest.
When the commission finds that a utility charged a customer more than an allowed rate, the utility must refund the full overcharge with interest.
The commission must approve or reject an electric utility's application to change rates or service within 300 days after it is filed.
The Public Utilities Commission must investigate fuel and power costs and report on its findings. The investigations cover how electric utilities pass purchased fuel and power costs to customers, deferred energy charges, ways to reduce rate effects, and practices that could reduce natural gas cost swings. The commission may adopt a cost-sharing system only if it finds that doing so is in the public interest. The commission must send progress reports to lawmakers and a final report on the investigations by July 1, 2026.
A utility must refund a customer for charges above an allowed rate or tariff. This applies when the commission determines that a utility charged a customer more than an applicable rate or tariff allows. The refund must include the full overcharge and interest.
The commission must issue a written decision on an electric utility's application to change a schedule within 300 days. This covers applications by electric utilities to change a schedule, including changes to rates or service. The 300-day period starts when the application is filed.
No hearings or votes scheduled.