If Senate Bill 947 also becomes law, dam owners would keep safety plans, and the department could use appropriated money for some emergency repairs.
Dam owners would keep current plans for monitoring, operating, maintaining, and securing their dams. They would report concerning findings and safety or security incidents within 24 hours.
The department could restrict dam operations to address significant harm, or order removal if serious harm is likely to continue. For immediate danger, it could order urgent repairs or other emergency steps.
Dam owners could apply for grants for repairs, changes, removal, or related engineering work, if they provide at least 10% of the cost. Emergency fund spending would require an appropriation and an owner unable or unwilling to act.
Dam owners would keep safety plans current and send required plans to the department for review. Owners must prepare plans for each dam they own; emergency action plans are required for their high- and significant-hazard dams. Owners must report concerning monitoring findings and safety or security incidents to the department within 24 hours. Emergency action plans cover high- and significant-hazard dams. Owners must report concerning monitoring findings within 24 hours and safety or security incidents within 24 hours.
The department could limit dam operations, order a dam removed, or take emergency steps when a dam poses an immediate danger. The department’s orders may address significant harm to people, property, or natural resources, or an immediate danger from a dam. Before ordering removal, the department must find that significant harm is likely to continue and give the owner a chance to correct the problem. Removal of a dam under the Michigan Public Service Commission’s or Federal Energy Regulatory Commission’s authority requires that regulator’s written agreement. Before a final order, the owner must have a chance for a hearing; after an emergency order, the department must provide a hearing opportunity within 15 days. The department must provide a hearing opportunity within 15 days after issuing an emergency order.
The text describes a dam safety emergency fund and grants for dam repair, alteration, removal, and related engineering work. Dam owners could apply for grants for repair, alteration, removal, or related planning and engineering work. The department may spend from the fund only after an appropriation and when an owner cannot or will not take corrective action. Grant applicants must provide matching funds of at least 10%. The department may spend from the emergency fund only when money is appropriated.
No hearings or votes scheduled.