Indiana’s environmental department follows limits on certain pollution risk values, while state agencies assign staff to help small businesses understand rules.
The department may not base a decision only on certain federal pollution risk values that have not gone through federal rulemaking. It must avoid using those values when they are at or below background levels in air, water, soil, or sediment.
Each state agency assigns a knowledgeable staff member to help small businesses understand a rule. The coordinator answers questions about requirements, deadlines, compliance, and penalties.
The department must decide within 90 days on complete applications to build or expand certain digestion or gasification facilities. The department and applicant may agree to more time; if the deadline is missed, the applicant may request a fee refund.
The department may not base a decision only on certain federal risk values that have not gone through federal rulemaking, and it must avoid values at or below background levels. This applies to decisions by Indiana’s environmental department. The rule covers listed risk values and assessments developed under the federal EPA risk information system or federal chemical control law. This provision took effect July 1, 2026.
State agencies assign a staff member to each rulemaking and each rule adopted from it to serve as a small business coordinator. This covers state agencies and small businesses affected by their rules; extra assistance information applies to environmental department rules. The coordinator must have relevant knowledge or experience and provide guidance in response to questions and concerns from affected small businesses. For environmental department rules, the coordinator may refer concerns about how a rule is applied or enforced to an environmental ombudsman. This provision took effect July 1, 2026.
The department must decide on a complete application for prior approval to build or expand a covered digestion or gasification facility within 90 days. This covers applications for prior approval to build or expand an anaerobic digestion or gasification facility, including one on a confined feeding operation’s premises. The facility may use biomass, appropriate feedstock, or both. Appropriate feedstock is a separated solid waste stream that can be processed for material or energy recovery. The department and applicant may agree to a longer review period. If the department misses the deadline, the applicant may request a fee refund, and the department must continue its review. The 90-day period starts when the department receives the complete application and required supplemental information. This provision took effect July 1, 2026.
No hearings or votes scheduled.