Local officials must decide complete building permit requests within set deadlines, except certain wireless projects; people can challenge how state building or fire codes were applied.
Local officials must decide complete building permit requests within 30 days, or 60 days for nonresidential projects and residential projects with more than 10 homes. Certain wireless projects follow separate rules.
People affected by building or fire officials’ decisions may appeal how state codes apply. Zoning or select boards serving as appeals boards hear only disputes about local changes to those codes; other appeals go to the state board.
Authorized local officials may order building rule violations stopped or fixed. People can contest an order. If a court upholds it and the correction deadline is missed, the municipality may fix the problem and claim its costs against the property.
Local building officials must decide complete building permit requests within 30 days, or 60 days for specified projects. The 60-day deadline covers nonresidential projects and residential projects with more than 10 homes. Certain requests to add or change wireless service facilities follow separate timing rules. Building officials set the minimum information needed for a complete request. The deadline starts when the complete request is submitted. The act took effect July 1, 2026.
People affected by building or fire officials’ code decisions may appeal how the officials applied state codes. A zoning or select board serving as a code appeals board hears only disputes about local changes to state building or fire codes. Other appeals go to the state board. An appeal must claim that an official read the code incorrectly, that a rule does not fully apply, or that an equally good or better building method is proposed. An appeals board cannot waive state code requirements. A local code appeals board’s decision may be appealed to the state board within 30 days.
Authorized local officials may issue written orders to stop or fix building rule violations. Orders cover state building rules, local rules made under them, and requirements in approved applications, permits, or decisions. Recipients may contest an order. If a court upholds the order and its correction deadline is missed, the local government may fix the violation and place a claim on the property for its costs. Recipients have 20 days after service to contest an order. Work must stop at once only if the order requires it.