Louisiana law requires advance notice and coordination for BEAD-funded broadband excavation and lets public safety officials stop work when they observe a likely violation.
For BEAD-funded broadband projects, excavators must notify utility operators at least 30 days ahead and try to agree in writing on the work and its timing.
If project markings are missing and an operator has not responded, excavators must give documented notice and wait three hours before starting work.
Public safety officials and local police may stop excavation or demolition when observed facts give them reason to believe the work violates the law.
Excavators on covered broadband projects must give operators advance notice and try in good faith to reach a written project agreement. This applies only to excavation connected to broadband projects funded in whole or in part through the federal BEAD Program. The notice is separate from and in addition to other notice required by law. If the parties cannot agree, that alone cannot delay excavation. Operators may follow the standard marking rules or a schedule already agreed with other operators for the project. The notice must come before excavation begins. This subsection ends August 1, 2030.
An excavator must give the operator documented notice and wait if markings are not visible and the operator has not said whether its facilities conflict with the work. This applies to excavation on a BEAD-funded broadband project when markings are not visible and an operator with facilities in the proposed area has not responded. After documented notice, the operator has three hours to mark the facility or report that there is no conflict. If the operator does not respond within three hours, excavation may begin with due care to protect underground facilities. The three-hour response period starts when the operator receives documented notice.
A public safety deputy secretary or local law enforcement officer may order excavation or demolition to stop when observed facts give reasonable cause to believe the work violates the law. The authority applies to excavation and demolition activities covered by this law. Work cannot resume until the excavator demonstrates compliance. Reasonable cause means facts observed by the officer that would lead a reasonable person to believe a violation is happening or about to happen. Work may resume only after the excavator demonstrates compliance.