A municipality may allow lead pipe replacement crews onto property, with advance notice to residents and owners and a follow-up letter to the owner.
A municipality may pass an ordinance allowing entry onto property for lead pipe replacement, with at least seven days’ notice except in an emergency. Entry must relate to the replacement work.
Before the work, the municipality must try to give owners and residents the date and time in person. If that fails, it must mail or post written notice with key details about the work and water service.
After replacement work is complete, the municipality must send the owner a certified letter saying about when the work happened and briefly describing it.
A municipality may pass an ordinance allowing it or a municipal water system and its agents to enter property for lead service line replacement. This applies to property within the municipality and covers the municipality, its municipal water system, and their agents. The owner and residents must receive notice at least seven days before entry, unless the municipality or water system determines there is an emergency. Entry is allowed only to perform lead service line replacement. Notice must be given at least seven days before entry, unless the municipality or water system determines there is an emergency.
The municipality must try to tell the owner and residents in person the replacement date and time. If they cannot be reached, it must send a certified letter or post a written notice in a prominent place on the property. This applies to the owner and residents of property where lead service line replacement is planned. The written notice must state the scheduled date and time, who will do the work, likely water service disruption, nearby places distributing extra drinking water if any, and remedies if workers cannot access the property. The notice is required before entry for replacement work; the text does not set a separate deadline for the in-person attempt or written notice beyond the seven-day entry notice.
After the replacement, the municipality must send the owner a certified letter with the approximate time the work occurred and a brief summary of the work. The letter goes to the property owner after lead service line replacement. The letter must be sent after the replacement is complete.
No hearings or votes scheduled.