The commission must set power connection rules by 2028, including protections for other customers and special requirements for data centers.
The commission must set or update rules for participating customers’ power connections and service. It must guard other customers against shifted costs and show certain generation charges separately.
Data centers connecting directly to the transmission grid must disclose other applications and cover assigned upgrade costs. Refunds are limited, and leaving early or failing to ramp up power use can trigger a fee.
Participating customers may join a new commission-approved program that shifts electricity use, if it creates no net costs for other customers.
Before the commission approves the new tariff, an electrical corporation may ask it to approve a data-center connection contract that meets the act’s requirements.
The Public Utilities Commission must set or update rules for connecting participating customers and serving them with electricity. The rules cover participating customers receiving retail electric service, including transmission, distribution, and generation service. The commission must assess risks and benefits for other customers and prevent stranded costs or cost shifts to them. For customers with separate generation charges, those charges must appear as a separate bill item. The commission must establish or update the rules on or before January 1, 2028.
The commission must create a transmission-level connection tariff with cost, disclosure, refund, and early-exit rules for data centers. These rules apply to data centers entering a new agreement to receive retail electric service at the transmission level. Data centers must disclose applications for the same facility in other utility areas or jurisdictions, and certify that they meet specified state resource requirements. The customer is responsible for transmission upgrades and use under a commission-set method. Refunds depend on actual revenue covering allocated costs and are capped at 75 percent of annual net transmission revenue. A customer that leaves within 10 years or fails to ramp up its power use as required must pay an early-exit fee tied to the projected revenue gap. This tariff applies to new data-center connection agreements made on or after January 1, 2027.
A participating customer may join a new demand-response program approved by the commission. The option is for participating customers and depends on commission authorization. The program must not create net costs for customers who do not participate and must support specified power-shifting, reliability, resource-adequacy, or emissions goals, as determined by the commission.
An electrical corporation may seek approval for a contract with a data center before the commission approves the tariff. The contract must be with a data center seeking transmission-level interconnection. The contract must meet the act’s requirements. This option covers facilities seeking retail electric service after January 1, 2027, and before the commission approves the tariff.
No hearings or votes scheduled.