California regulators would drop an earlier state-funding cutoff for some pump hydroelectric projects and allow energy-only resources to meet procurement requirements when feasible.
When setting electricity procurement requirements, regulators must allow energy-only resources to meet them as much as feasible. They must consider clean energy goals, storage charging, and resource diversity.
The Department of Water Resources may procure power from a pump hydroelectric facility up to 500 megawatts without requiring it to have received state funding before 2023. Procurement still depends on a commission request.
The California Public Utilities Commission must allow energy-only resources to meet procurement requirements to the greatest extent feasible. This applies to procurement requirements, including one-time orders and ongoing programs. When setting procurement requirements, the commission must consider how energy-only resources affect clean energy deployment, storage charging during off-peak periods, and resource diversity. This requirement applies when the commission requires procurement under the amended section.
The Department of Water Resources may procure resources from a pump hydroelectric facility without requiring that it received a direct state appropriation before January 1, 2023. The rule covers resources from pump hydroelectric facilities that meet the size limit. The facility may not exceed 500 megawatts. The commission must first find a need for eligible energy resources, specify the resources, and may request procurement. The department may procure only after such a request and before January 1, 2035. The department may procure resources before January 1, 2035, after receiving the commission's request.
No hearings or votes scheduled.